Chorley Remembers Secretary, Steve Williams and Chorley Council Officer, Jamie Dixon, met contractors on-site this morning to review progress.

Nine panels with the names of the fallen were already up and a phone call from the stonemasons, MJR Masonry Services, at the end of the day confirmed that they had erected a further four; that just leaves three more to do, before they start on the coping stones.

Workers from main contractors, Landscape Engineering Ltd., have finished the random stone wall either side of the new memorial, starting on rendering the back of it; they also made a start on the block paving around the site.

The project is scheduled to be completed by Monday, 5th November and Project Manager Steve Williams is confident that everything is well on track.