Here are the latest photographs and a video report from the site today (Saturday).
The relocated Falklands stone has been set in concrete and more concrete has been poured into the foundations for the new low screen wall.
The Portland Limestone panels have arrived at the engravers in Hampshire from the quarry.
Work will start on engraving the 741 names on Wednesday and that should take about a week.
Two flagpoles have been ordered and we have just to order a balustrade for the raised platform at the rear of the site – the latter will be will used by those conducting any services or acts of remembrance, becoming a viewing platform for the rest of the time.